Soil Mechanics Homepage

Built Environment CL Associates ECS Global Soil Mechanics TES Bretby

 

 
Environmental Services Group
Soil Mechanics Homepage
Materials Testing Services
About Us
Services
Case Studies
Contact Us
 
Environmental Sciences Group

Medway Viaduct - Refurbished for the next 40 yearsSoil Mechanics Homepage

The River Medway poses a significant obstruction to the transport routes from London to the Dover ports and Channel Tunnel and with todays traffic volumes a high capacity crossing is essential. The problem is that the existing viaduct is simply not up to the job, although it is not totally a lost cause. The solution from CSM (Costain, Skanska, Mowlem) Joint Venture working under contract to the highways agency sounds straight forward enough: build a new viaduct alongside the old one, divert the traffic onto that, refurbish the old one and then use the new viaduct for traffic from the coast and the old one for traffic from city, doubling the original capacity.

Concerns over potential chloride attack from road salt penetration into the deck of the old viaduct were one of the many problems that had to be addressed to ensure the future life of the structure. This would need a detailed survey covering the entire 1km length of the viaduct, a deck area almost 30,000m2, a huge task in itself and one which was taken on by the Materials Testing Division of Soil Mechanics.

The process adopted by Soil Mechanics included non-destructive investigation, visual inspections, material sampling and laboratory testing to identify the areas suffering chloride attack and in need of repair.

The first part of the process comprised non-destructive surveying using 'half cell' potential meters to identify areas of elevated chloride content. Once the tarmac surface had been stripped by the main contractor, the walk over half cell surveys were carried out by Soil Mechanics technicians over the entire viaduct deck in 6m squares. A colossal task with readings taken at 0.5m intervals: 144 readings per square, well over 100,000 readings in all.

Results from this survey enabled the areas of potentially elevated chloride content to be delineated. Samples from three different depths were then taken from these areas and from a control location in each of the 6m survey squares for laboratory testing to determine the precise levels of chloride. In total 8,000 chloride tests were carried out and this required the utilisation of four commercial laboratories to complete the testing within the contract period.

The chloride attack survey was completed by a thorough visual and sampling inspection of the joints and the bridge underdeck from self elevating platforms and specially constructed gantries.

Repair work by the main contractor to affected areas followed however particular attention is required to avoid damaging the existing buried reinforcement. To ensure this was not damaged during the repairs, Soil Mechanics provided 'Cover Survey' information on the location of reinforcement across the whole of the viaduct deck.

Voiding was also considered a potential problem within the grouted pre-stressing tendon ducts. Under the direction of Soil Mechanics, this work was carried out by materials specialists Sandbergs. The tendon duct surveys comprised drilling and borescope surveys with the results being presented as in descriptive and photographic format.

The project valued at £140k saw Soil Mechanics working alongside the main contractors for some four months.

Environmental Services Group Homepage
Soil Mechanics Homepage

Geocone
Geotech
Pelorus Surveys

top

Environmental Sciences Group
Environmental Sciences Group